General Meeting Information
Date: October 14,
2025
Time: 2:00-3:00pm
Location: Via Zoom*
*Contact the Administrative Assistant for the Zoom link
-
Agenda
Time Topic Purpose Draft Notes 2:00-2:05 Welcome and Introductions I Welcome 2:05-2:10 Review and approve mission and membership A Mission approved. New committee members confirmed and welcomed. 2:10-2:15 Review and approve meeting calendar A The committee will now meet monthly instead of quarterly. Poll will be send out to determine Nov./Dec. meeting date. 2:15-2:20 Review Best Practices document for DASG I Reviewed expectations for shared governance and student participation. Note: Future edits DASG to correct references from “DASB” to “DASG.” 2:20-2:25 Review and approve notes from May 6, 2025 meeting A Approved 2:25-2:35 Resource Hub - formerly the Food Pantry I The Hub (formerly the Food Pantry) relocated to the Baldwin Winery (lower level, north side near Lot 8). Offers food, cleaning supplies, clothing, and transportation assistance (e.g., shuttle vouchers).Open weekdays with varying hours—students should check the website before visiting. 2:35-2:55 Measure G Update I Completed/Closeout Projects
- Beach Volleyball Conversion: Renovated softball field into six NCAA-regulation volleyball courts. ADA upgrades, new signage, and lighting installed. Currently in use by PE and Athletics.
- Flint Center Demolition: Site fully cleared and landscaped for future development (Creative Arts Building site).
In Construction- Roof Upgrades (E3, S4, S5): Conversion to single-ply roofing and siding repairs.
- Restroom Renovations (S2, S6, L5): All-gender conversions; completion expected Summer 2026.
In Design/Planning- PE Complex Renovation: Funded jointly by the State and Measure G. 76,000 sq. ft. modernization (excluding the pool). Includes seismic, HVAC, and accessibility upgrades. Design submission: January 2026; Construction start: Summer 2027.
- Campus Center Lighting, Flat Roofs, and EV Chargers: Early-stage planning.
Creative Arts Building – Presentation by Aaron Forbes (DLR Group)- Site located where the Flint Center once stood.
- Will replace Buildings A8 and A9.
- Includes:
- Studios for photography, ceramics, sculpture, painting, digital arts
- Art history lecture hall
- Student collaboration areas and outdoor learning spaces
- Focus on sustainability, flexibility, and strong campus connection via the Sunken Garden.
- Timeline: Design through 2026 → Construction start in 2027 → Target completion ~2029.
Campus-Wide Impacts & Relocation Planning
Major upcoming construction (PE Complex & Creative Arts) will require temporary relocations.- Potential use of temporary trailers and shared campus spaces.
- Campus community may be asked to accommodate displaced programs.
Future Projects & Maintenance Updates- Tennis Courts: Resurfacing and restriping for pickleball.
- VPAC Lighting Upgrade: Recently completed, additional improvements pending.
- Campus Center Remodel: First-floor refresh planned.
- Lighting Upgrades: Transition to LED campus-wide.
- Partnership with Santa Clara County Housing Department: Mobile health trailer to operate from Parking Lot J daily. Long-term vision: permanent health services facility in Lot B.
- Tree Maintenance: 124 trees scheduled for trimming (including RSS area). Work delayed to avoid academic disruption.
2:55-3:00 Information sharing/quick news I Flu shots available to students, staff, and faculty while supplies last A = Action
D = Discussion
I = InformationTopic Start time Campus Facilities Committee 10/14/25 13:55 End time 10/14/25 14:56 Name (original name) Duration Aaron Forbes | DLR Group 43 ADM106 51 Audrey Tai 62 Benny 1 Benny Lin | DLR Group (Benny, DLR Group) 49 Brian.Huddleston | Director of Design-Build 18 Cindy Lee 55 Claire Hinchman | DLR Group 41 Crystal 31 Daniel Acosta 58 Ethan Brignetti 52 Farhad Sabit - De Anza 56 Jamie Pelusi 56 Kathy Munson 58 Kristin Skager 25 Margarita Hawthorn 56 Michael Moreno 55 Myles Vongnakhone (smile) 57 Oscar Guillen 60 Pippa Gibson 62 Ron Hannon 57 Rosafel Nogra 59 Roseanne Sciacchitano 36 Sarah Lisha (she/her/they) 56 Stacey Carrasco 61